Rise, run, and slope length
The third of rise, run, and slope length from any two, with the grade they make as a percent, an angle, and a labeled ratio.
A rise of 2.5 ft over a run of 30 ft is a 8.333% grade, 30.104 ft along the slope.
- Slope length
- Rise
- Run
- Slope angle
- Ratio H:V
- Ratio V:H
Provenance
- Computed by
- survey.earthwork.rise-run 1.0.0, core 0.1.0
- Model
- Grade g = rise / run; slope length = √(rise² + run²); from a slope length, run = √(slope² − rise²) or rise = √(slope² − run²); percent = 100·g, angle = atan g
- Accuracy
- Exact
- Notes
- None
- Cites
- Ghilani, C. D., and Wolf, P. R., Pearson, Elementary Surveying: An Introduction to Geomatics; Federal Highway Administration, Noise Barrier Design: Terminology
Something look off?
How we got thisFormula, worked example, sources, and proof
Model: Grade g = rise / run; slope length = √(rise² + run²); from a slope length, run = √(slope² − rise²) or rise = √(slope² − run²); percent = 100·g, angle = atan g
Accuracy: Exact
When to use this: Use this when you have measured two sides of a slope and need the third: the rise and run of a ramp, a taped slope length and a height difference, or a slope length and its horizontal distance. Enter any two of rise, run, and slope length in the same units. The tool returns all three with the grade as a percent, an angle, and a ratio labeled H:V and V:H.
Limitations: This is one straight slope as a right triangle. A rise found from a run and a slope length is reported as positive, since the two lengths cannot say whether the ground climbs or falls. The slope length must be longer than the other side given. It does not reduce a total-station shot with instrument and target heights, and it gives no design advice on what slope will stand.
Worked example: A 2.5 ft rise over a 30 ft run. Source: 2010 ADA Standards sec. 405.2: a 1:12 ramp (8.333%), here a 30 in rise over a 30 ft run. It is golden test vector v001, and every build checks the tool still gives its answer within its tolerance.
You enter
- Rise
- 2.5 ft
- Run
- 30 ft
You get
- Percent grade
- 8.333
- Slope length
- 30.104 ft
- Rise
- 2.5 ft
- Run
- 30 ft
- Slope angle
- 4.7636°
- Ratio H:V
- 12H:1V
- Ratio V:H
- 0.083V:1H
- Per mille
- 83.33
Review: Not yet independently reviewed by a licensed surveyor.
Last verified: 2026-09-23, when a maintainer last confirmed this tool's sources at the issuer. See the sources ledger.
Status: version 1.0.0, core 0.1.0. See this tool in the verification report.
Checked against: 24 golden test vectors (download the test vectors, each with its source and tolerance). See how results are checked and every source.
Sources
- Elementary Surveying: An Introduction to Geomatics, Ghilani, C. D., and Wolf, P. R., Pearson, 16th edition. Grades and slopes in route surveying and construction layout.
- Noise Barrier Design: Terminology, Federal Highway Administration, Web page, read 2026-10-13. Grade: a 20 m rise over a 400 m roadway is 5%, calculated as 20 / 400 × 100.